Many days of planning, discussing, designing and coding lay behind us: More than 50% of the work on streetfiles.org is completed. We still have a fair bit of work in front of us but the launch in spring 2008 is slowly coming into reach.

These screenshots show the state of development:

screenshot 01

screenshot 02

Some technical facts:

  • Number of team members: three
  • Lines of code (till now): 27.460 PHP, 1.2175 CSS & 5.155 HTML
  • Tables in database: 32
  • Number of design mockups: 36
  • man-days (roughly): 80
  • beers: 57 some

6 Responses to “Behind the scenes”

  1. Graffr Says:

    Hey, slow down. You’re moving too fast! ;-)

  2. movel Says:

    this are a lot of good facts. so lets keep drinking for a faster launch…

  3. Graffr Says:

    Launch in spring 2008? That’s a joke, right? You’re working with 3 guys! Maybe you should consider cutting on the beer then ;-)
    But seriously, you ARE kidding, right?

  4. oli Says:

    @Graffr
    a team of 3 means:
    1 Designer
    1 Developer
    1 Guy for PM, incentive, communication & contacts

    We are not working fulltime on that project, some clientjobs are still to do …
    but don’t care we are in a hurry.

  5. Graffr Says:

    Ah, I thought you had 3 coding guys working all at once.